CHAPTER 9 SCHEDULING: PROGRAM EVALUATION AND REVIEW TECHNIQUE NETWORKS AND LINEAR OPERATIONS
9.1 Introduction Bar charts and critical path method (CPM) networks assume that all activity durations are constant or deterministic. CPM: 공기가 일정하다는 가정 The variability of project activities is addressed in a method developed by the U.S. Navy at approximately the same time as CPM. This method was called the Program Evaluation and Review Technique (PERT). PERT: 공기가 변동 가능하다는 가정 The duration of some or all of the project activities can be variable. The variability is defined in terms of three estimates of the duration of each activity as follows: 3가지 공기 Most optimistic duration (ta) 낙관적 공기 짧은 공기 Most pessimistic duration (tb) 비관적 공기 긴 공기 Most likely duration (tm) 가장 가능성이 높은 공기 최빈 공기 평균 공기: Expected duration, te = [ta + 4 tm + tb] / 6 (베타 분포를 가정하여 추정) 공기의 분산: σ2 = [(tb − ta ) / 6]2 (베타 분포를 가정하여 추정)
FIGURE 9.1 Selected areas under normal distribution 9.1 Introduction [ta + 4 tm + tb] / 6 [(tb − ta ) / 6] 1 2 3 FIGURE 9.1 Selected areas under normal distribution
9.1 Introduction Central Limit Theorem 중심극한정리 확률변수 합계의 분포는 확률변수의 원래 분포와 상관없이 충분한 개수를 합하면 (보통 N > 30) 근사적으로 정규분포를 따른다. Suppose m independent tasks are to be performed in order; (one might think of these as the m tasks that lie on the critical path of a network). 주공정 상 액티비티들의 공기의 합 프로젝트의 공기 T = t1 + t2 + … + tm T는 주공정 상 작업들의 작업시간의 합계 시간 ET = T = Et1 + Et2 + … + Etm ET는 주공정 상 작업들의 작업시간의 합계 시간의 평균 VT = 2T = Vt1 + Vt2 + … + Vtm VT는 주공정 상 작업들의 작업시간의 합계 시간의 분산 T ~ N(T, 2T) T는 평균이 T 이고 분산이 2T 인 정규분포를 따름
9.2 An Example Program Evaluation and Review Technique Network 평균: te = [ta + 4 tm + tb] / 6 분산: σ2 = [(tb − ta ) / 6]2 주공정로 #1 Node Arc 주공정로 #2 FIGURE 9.2 Small PERT network Activity on Arc (AOA) 방식 (참고: Activity on Node (AON) 방식)
9.2 An Example Program Evaluation and Review Technique Network The variance of path two (5.416) is greater than that of path one (3.694). Because this means a greater spread of the probable total project durations, the variance of path two is selected as the variance to be used for further PERT calculations. 평균이 같다면 분산이 더 커 변동성이 더 큰 주공정로를 선택하여 분석 주공정로 #1 주공정로 #2
9.2 An Example Program Evaluation and Review Technique Network 분산 표준편차 = 분산1/2 24.5 = + 3 = 17.5 + 3 2.327 24.5일 이내에 끝날 확률이 99.7% FIGURE 9.3 Normal distribution of total project durations for small PERT network
9.2 An Example Program Evaluation and Review Technique Network What if we want to know the probability of completing in 19 days? 19일 이내에 끝날 확률? Consulting the cumulative normal distribution function table given in the appendix with a Z value of 0.644, yields a value of 0.7389 or 73.89% probability of completing the project in 19 days. Z값을 구한 후 정규 분포를 이용하여 확률 계산 What would be the probability of completing the project in 17.5 days? 50% : 정규분포는 좌우 대칭 What would be the probability of completing the project in 16 days? 50% 미만 평균 이하 1.5
9.2 An Example Program Evaluation and Review Technique Network 19 N(17.5, 2.3572) - + 17.5 -32.357 17.5 -22.357 17.5 -2.357 17.5 17.5 +2.357 17.5 +22.357 17.5 +32.357 N(0, 1) 표준정규분포 73.89% - + -3 -2 -1 +1 +2 +3 0.644
9.3 Program Evaluation and Review Technique Shortcomings In fact, the PERT results are too optimistic. PERT 예측 공기는 지나치게 낙관적 The method of using the te value to determine the longest path through the project network and assuming that the duration of this path is the most probable value for the total project duration is not totally accurate: 프로젝트의 공기는 보통 PERT 예측 평균치보다 길다. Merge Event Bias: 주공정 상에 우연히 일찍 끝나는 액티비티가 있는 경우, 다른 경로가 주경로가 될 수 있으나, 이런 경우는 PERT에서 고려하지 않는다. Monte Carlo Simulation 이용. Activity가 서로 독립이라는 가정 FIGURE 9.4 Merge event bias
9.4 Linear Construction Operations Often construction sites have linear properties that influence the production sequence. 선형성 : 동일 작업의 반복 A road job may be subdivided into 14 sections that must be completed High-rise building : erect formwork, install reinforcing steel and embedments, and pour concrete. 거푸집 배근 콘크리트 Tunnels : drill, blast, remove muck, and advance drilling shield. 드릴 폭발 청소 전진 Gradient : 경사도 인도와 차도 사이의 연석 FIGURE 9.5 Road project divided into 14 sections
FIGURE 9.6 Production curve 9.5 Production Curves Production curve reflect the production rate or speed with which sections or units are being processed. 시공 속도 Demobilization 철수단계: 느림 계획 빠름 Mobilization 착수단계: 느림 실적 FIGURE 9.6 Production curve
FIGURE 9.7 Velocity diagrams for a road construction project 시작구간 종료구간 9.5 Production Curves 0% 30% 80% 100% 4 3 2 1 12주차의 진도 1. Both rough and finish grading should be completed. 2. Approximately 80% of the aggregate base has been placed. 3. Placement of the 5-inch concrete base is approximately 30% complete. 4. Placement of 9-inch concrete is just commencing (개시). 1: 100% 2: 80% 3: 30% 4: 0% FIGURE 9.7 Velocity diagrams for a road construction project
FIGURE 9.9 Unbalanced process production rates 9.5 Production Curves Ripple effect (파급효과) causes shutdowns of process B and C. A, B, C 작업 간의 간섭 : A B C Slopes of the curves are parallel : 작업 중단을 방지하기 위해 작업 속도를 균일하게 유지 B 중단 C B가 A의 간섭을 받지 않는 경우의 Production Curve FIGURE 9.9 Unbalanced process production rates
오늘 4번 공정을 마친(4번 체크포인트를 통과한) 주택들은 8주 후, 즉, 12주 차에 완공되어야 한다. (지연시간) 따라서 오늘 시점에 8주 후 완공될 주택 수만큼의 물량(7채)이 4번 공정을 마친 채 대기하고 있어야 한다. 9.6 Line of Balance 적정 진도선 1940s, line of balance (LOB) was first used in the manufacturing industry 제조업에서 시작 10 apartments are supposed to be created over the course of 15 weeks 15주 동안 10채의 주택 공사 (9개 공정으로 구성) 8주 후 필요한 물량이 지연시간으로 인해 지금 만들어져 있어야 함. 계획 속도 1채/주 현재 진도가 딱 맞는 공정 진도가 빠른 공정 0.5채/주 진도가 느린 공정 시작 시점 (공정) 현시점 : 종료 시점 (공정) Lead Time 지연시간 : 4번 공정은 준공 8주전에 완성되어 있어야 함 시작 시점 (공정) 종료 시점 (공정) FIGURE 9.10 Line-of-balance example
9.7 Line of Balance Applied to Construction High-rise building example Each floor section must be processed through the following work activities: 각 층 각 구역에 대해, 다음 공정 반복 수행 1. Erect forms 거푸집 짜기 2. Place reinforcing steel 배근 3. Place concrete 콘크리트 타설 4. Dismantle forms 거푸집 제거 5. Place curtain wall 커튼월 설치 6. Place windows 창문 설치 N+ N+ N+ N+ N+ 각 층 구역별 작업 순서 FIGURE 9.11 Schematic of floor cycle work tasks
9.7 Line of Balance Applied to Construction Progress Monitoring Points 1 2 3 3 4 5 6 Production Plan Lead Time 지연시간 Hours Objective Chart 확대구간 작업속도 1층/주 4구역/40시간 작업속도 1.5층/주 6구역/40시간 작업속도 1층/주 4구역/40시간 FIGURE 9.12 Program chart and objective
9.7 Line of Balance Applied to Construction 작업속도 4구역/40시간 26구역의 Window 작업이 완료되었다면, 32.4 구역의 Elect Form이 종료되어 있어야 한다. LOB(1) = 26 LOB(2) = 26 + (6/40)2 = 26.3 LOB(3) = 26 + (6/40)8 = 27.2 LOB(4) = 26 + (6/40)14 = 28.1 LOB(5) = 26 + (6/40)38 = 31.7 LOB(6) = 26 + (6/40)40 = 32 LOB(7) = 32 + (1/10)(42 − 40) = 32.2 LOB(8) = 32 + (1/10)(44 − 40) = 32.4 작업속도 6구역/40시간 Line of Balance: 적정 진도 좌우로 대칭 FIGURE 9.13 Enlarged projection of program chart onto objective chart